Some notes from Day 1 & 2 of the BCUC review of VIGP.
Monday, June 16
Tuesday, June 17
Coast Bastion Hotel, Nanaimo
On the first day of the hearing, there was considerable discussion about BC
Hydro going to the market with a request for tenders (RFT) for firm energy
proposals as alternatives to GSX/VIGP. Norske, for example, would submit
their proposal under such a procurement process. Hydro's thinking is
that neither the Norske nor the Terasen offerings are specific enough either
in technical or financial terms, for Hydro to have confidence that putting
VIGP/GSX aside would be prudent.
Hydro's thinking is going further with this. They are envisioning that
the BCUC may grant them a CPCN that requires them to undertake such a
procurement process. And they are saying, they want that CPCN so they
have a fallback, and may proceed with VIGP/GSX, should the RFT process fail to
elicit a satisfactory alternative.
Hydro has two particular deadlines in mind. The first is January 2004,
which is the latest date, they aver, by which they can place an order for a
turbine for VIGP (remember that at the end of April they paid GE a penalty of
some $35 million or more, when they cancelled the original turbine order that
had been placed in November 2000), and be assured that they can have VIGP
ready to go, hooked up to GSX, and tested, by the critical deadline of 2007.
The second date that concerns Hydro is March 15, 2004. If by that date,
the permitting outcomes from the NEB and BCUC are not known, apparently the
deal with Williams terminates, and Hydro may be on the hook to compensate
Williams for all their costs (plus penalties, presumably) incurred to date.
So, on day 2 (Tuesday), in answer to questions from the BCUC, Bob Elton
of BC Hydro said that he had been thinking about these matters, and, well,
here are his own words from the transcript: (Day 2, page 256)
We can’t not start such a [request for tenders or RFT] call and then in
October have a decision that says there must be a call and then
complete a call by January. That couldn’t happen. And I think there’s
two issues to think about. One is the process has to be fair and has to be
one that people believe in, otherwise they won’t bid, and in addition, the
result may not be fair. And second, that has to be quick enough that it can
meet everybody’s needs.
So I think that -- I haven’t checked our timetable in detail. I think we
would have to make a decision within the next two weeks as to whether or not
we should go ahead with the call, and just make some assumptions about what
the Commission’s decision might be.
From my point of view it’s a risk issue. In other words, I can imagine,
without predicting what the decision might be, that there is a high
likelihood that we’ll be required to make such a call, therefore we
certainly need to start planning one and we need to decide within the next
week or so whether or not we should initiate one.
This is discussed in more detail by Mary Hemmingsen, from Panel 2, beginning
on page 330.
Are these the hasty makings of an exit strategy for VIGP & GSX?
But what's central to this whole matter, and what is unlikely to get examined
in much detail by Terasen, Norske, JIESC, Elk Valley Coal Corp, etc., is the
whole question of whether we need all this power at all on Vancouver Island,
and how much power we actually do need, and by when.
BC Hydro has branished their "lights will go out" threat since they
went public with GSX in 2000. Originally that was going to happen in
2004, and it has moved away year by year, and is now pegged in 2007, when they
derate to zero (note, not retire or decommission) the HVDC system.
Hydro's also points at their load forecasts which show steady growth from the
present, year after year.
The fact of the matter is, however, that load has remained effectively level
in the previous decade - all the way back to 1992. It fluctuates from
year to year, but the trend is level. Population, industry, and
employment growth prospects on the island in the next decade are, as well,
gloomy. There is no sound basis to predict anything other than the gentlest
of growth forecasts, certainly not the 30 to 40 MW per year peak capacity
growth that Hydro comes up with.
The GSX Concerned Citizens have challenged Hydro's supply, load, and
forecasts. We commissioned a study, which we used as evidence
in the GSX hearing, and will use more extensively in the BCUC proceeding.
It is by Steve Miller & Associates. You can obtain it at
http://www.sqwalk.com/VISupplyDemand.pdf.
The conclusions from that study are that supply has been understated, load
overstated in the forecasts. I can send you a copy, and put you in touch
with Miller if you wish.
We have challenged Hydro's marketing and PR vice-president, Shawn Thomas, with
respect to these matters. At the end of 2001, he left BC Hydro.
We have challenged their senior planning engineer, Kelly Lail, and he is no
longer with BC Hydro. Recently, Hydro's forecasting authority, Henry Mak,
was suddenly disappeared from BC Hydro.
Interesting that these three people - Thomas, Lail, Mak - who have
played such a pivotal role in the evolution of GSX/VIGP, are gone. A
quick scan of the expert witnesses that Hydro is putting forward now to
defend these projects have a surprisingly short life either in Hydro, or in
their present jobs. 2 years, 1 year, a few months in some cases, a few
days in others. Henry Mak's replacement as Manager for Load
Forecasting is Dennis Nelson. He's in an acting capacity, and has been
doing the job since June 8.
The impact of large industrial power users on the system, our system, is
generally not recognized. It is news to me, for example, that 100 of
BC's industrial users, use 70 percent of BC's energy. How about this:
The three mills that Norske Canada has on Vancouver Island use 90 percent of
the transmission capacity to the island, and about a quarter of the energy
distributed on the island. The loss of one mill would free up between
100 - 200 MW.
The most recent evidence filed by BC Hydro in the BCUC proceeding shows a
drastic recalculation of "adjusted peak" demand over the last ten
years, reducing the previously published "peak" figures, bringing
them more in line with "actuals", and more in line with the findings
in the Miller evidence.
These "adjusted peak" figures are the starting point for their
forecasts, and the recently adjusted, adjusted numbers, substantially weaken
Hydro's argument that peak load is a challenge to meet with available supply.
Thus, they have all but given up talking about any critical dates, other than
2007, when the rating of the HVDC falls to zero. Note, that's the rating
of the HVDC, not it's actual capacity to carry energy, which it will continue
to do.
Steve Miller's cross-examination of Hydro's Panel 2 on Tuesday addresses these
questions. He begins on page 364.
The first gem he elicits, is this: Hydro's earlier peak calculations are
simplistic and lead to inappropriate results. Does that mean, forecasts
based on these calculations are inappropriate?
Here's Dennis Nelson:
That simplistic approach did not provide appropriate results. What we did in
the last few weeks is dig into the actual process of assembling a peak
forecast itself, where we get from distribution planning not just whether
normalized forecasts for the next year, but you get weather normalized
actuals or estimated actuals for the year you’ve just gone through. And it
makes a lot more sense and a lot more transparency to the system to use that
kind of data when we respond to questions like this.
in finding out what data is available to us, it became clear that at the
substation level we were getting information that should have been used to
answer your questions two and a half years ago. That had not become clear
in the interim period, and it came clear through a rather diligent study
as to what information was around and how best to portray this very
complex question of weather normalization.
Steve Miller, on being told he can't take some time to consider the
information that has just been released, that he has been asking for for two
and a half years:
I would like to point out that what's at issue here is a number of
megawatts equal to very close to the plant we're talking about, so this is
not a trivial issue. This temperature adjustment is one of the most key
things in our evaluation of the proponent's claim that their lights are
going out or not.
MR. MILLER: Q: And I’m sure -- I’ll ask it to you, but I know your
answer and I’m going to ask. The risk that you see within your company is
a risk of delivery or non-delivery of your product.
MR. NELSON: A: Yes.
MR. MILLER: Q: So if the lights dim you consider that you took too much
risk. On the other side is the risk that you spent too much of the
public’s money to mitigate that risk and that’s where the Commission
will decide.
MR. NELSON: A: That’s correct.
MR. MILLER: Q: How much should be spent. But it’s good that the Commission
gets to see what part of your position is your company’s view of risk and
your company’s view of actual data.
MR. NELSON: A: Yes.
How about this: Dan Potts represents the large industrial electricity
users. And Hydro is pissing them off. What JIESC want is
transmission enhancement, so the island can buy from the mainland generation
market, and mainland generators can sell to Vancouver Island.
Coal-fired power.
MR. POTTS: Q: You’re telling the Joint Industry Electricity Steering
Committee that the best B.C. Hydro can do is develop new power projects
using $6.00 gas?
MS. HEMMINGSEN: A: I think that’s a sensitivity that we tested. The
basic case is the $3.00 U.S. value.
MR. POTTS: Q: And there are no options to do better than that?
MS. HEMMINGSEN: A: Well, I guess B.C. Hydro has a number of Resource Smart
options, which might come in under that amount, but going forward the
benchmark price is the market price of electricity.
MR. POTTS: Q: I think that ends my discussion. Thank you very much.
Other notes:
Snuneymuxw First Nation are not participating in this proceeding, but are
monitoring.
Ministry of Energy & Mines are also not participating, but are
monitoring.
Hydro's rationale for the project seems less related to forecasts, and
more to the retirement of the HVDC. This could be to reduce
attention on the forecasts (see story above).
Inconsistencies in the story about running VIGP as a base plant. The
application says they'll run it at 90% capacity, or 90% of the time.
Bev van Ruyven (I think) quibbled about 87% one year 88% another year 90%
another year and so on. In cross-examination, it sounds like they
might be more opportunistic, and not run it as a base plant at all.
In some ways, it's like they're going to buy a Hummer, and they say
they'll drive it all the time. But then sometimes they'll drive the
family car, or ride a bike or walk - whatever's cheaper.
Claiming that they'll move gas from the GSX interconnect at Shawnigan Lake
to Duke Point and Elk Falls at no cost. Haven't explained that yet.
Tersasen's counsel was curious about that statement, too.
With respect to selling GSX and VIGP, Elton said they would act
commercially unless directed by government to act otherwise.
---END---