VIGP Daily
Hearing Summary For July 3 - Final
DAY 13
After a series of preliminary
matters the day commenced with BC Hydro Panel
No. 7.
BC Hydro Panel No. 7
(Bob Elton, Dawn Farrel, Mary Hemmingsen) - Call for
Tender Process:
BC
Hydro panel No. 7 was put up in order for intervenors to examine further
the
Call for Tender ("CFT") proposal from BC Hydro. However, before the
subject
of the CFT was reached the panel commenced with a discussion
regarding the
costs of the TGVI proposal and GSX. These issues will be
addressed in written
argument. The Commission Chair put forth a suggestion
for further
negotiations between BC Hydro and TGVI with the goal of reaching
an agreement
on a model to be used to cost the two competing proposals, TGVI
or GSX. A
joint submission on the model would be made to the BCUC by July
14, 2003. Any
outstanding inputs that the two parties could not agree on
would be described
and the BCUC would make a ruling as to which input should
be used. BC Hydro
and TGVI both agreed that they would enter into such
negotiations.
Norske
Canada cross-examination of Panel No. 7:
Norske began their examination with
a discussion regarding a schedule of the
costs of the CFT process that BC
Hydro had presented as an exhibit. This led
to a discussion as to whether or
not BC Hydro would sell the rights to take
over VIGP for costs less than
those incurred to date, what the bid process
would be for VIGP if the project
was to be sold, and would BC Hydro accept a
BCUC direction that assets not be
sold for less than the amounts expended.
BC Hydro stated that the CFT
comparison has to be made on incremental costs
and that BC Hydro must find
the lowest cost alternative for its ratepayers.
Norske queried whether or not
consultations between BC Hydro and bidders
would be made part of the CFT
process. BC Hydro confirmed that this would be
the case.
Terasen Gas
(Vancouver Island) Inc. ("TGVI") cross-examination of Panel No.
7:
TGVI
agreed to provide an electronic copy of its cost of service model. TGVI
asked
a series of questions regarding the cost of the CFT process. The
question was
asked as to whether or not BC Hydro would bid into the CFT
process. BC Hydro
answered that BC Hydro would not bid into the process with
VIGP, but that the
costs incurred to date on VIGP would be used as a
reference price. The timing
of the CFT process was scrutinised as was
capacity that BC Hydro holds on BC
gas pipelines and whether or not that
capacity would be made available for
bidders. BC Hydro stated that the
capacity was for ICP and would not be made
available.
GSXCCC cross-examination of Panel No. 7:
GSXCCC begin its
cross with a question that asked how BC Hydro would put
VIGP on the market if
it still did not have a CPCN and how would that
project be described to
potential investors. BC Hydro replied that the more
certainty there is in
VIGP the better the deal that BC Hydro could negotiate
for its ratepayers and
as a result, BC Hydro would hope that the BCUC had
issued by that time a CPCN
for the project. The point was made that only BC
Hydro would require a CPCN,
an IPP would not. However, IPP's would be
expected to have any EPA approved
by the Commission under section 71 of the
Utilities Commission Act. GSXCCC
also queried the fairness of the CFT
process. It was explained that the CFT
will require interim reports from the
reviewer and that if the process was
not fair, in the reviewers opinion,
this would be revealed before the end of
the process. The reviewer would be
involved in the designing of the criteria
for the CFT.
The GSXCCC asked questions regarding a limitation on the IRR
for bidders to
the CFT. BC Hydro's view is that some sort of a threshold IRR
would be
probable. BC Hydro also stated that any demand side management
proposals
that were bid into the CFT would not be limited to Power Smart
terms. BC
Hydro also stated that Resource Smart projects would not be bid
into the
CFT.
BCOAPA cross-examination of Panel No. 7:
The BCOAPA
opened with questions regarding the option on the VIGP land that
BC Hydro has
exercised. There were also questions regarding Powerex capacity
contracted on
the GSX, near-commercial processes that may be considered and
whether wind
would be able to meet BC Hydro's capacity requirement. BC Hydro
answered that
it would not.
Commission Counsel had no questions for Panel No. 7.
Maxim
Power Corporation ("Maxim") Panel:
Maxim is an IPP that is in the business of
co-generation projects. Its
evidence in this hearing is that there should be
a greater emphasis on
co-generation by BC Hydro.
GSXCCC cross-examination
of Maxim Panel:
GSXCCC opened with some queries regarding the history of
Maxim and questions
as to what Maxim considers to be co-generation. Maxim
uses various differing
fuel sources including land-fill gas, anaerobic gas,
and natural gas. The
availability factor of their plants is 92 to 94 per
cent. Maxim estimates
that the co-generation capacity on Vancouver Island is
about 60 MW. Maxim
also does not believe that CCGT's should be used as a
proxy for mainland
generation, as BC Hydro has done in its portfolios, but
that co-generation
facilities should be used instead.
BCOAPA
cross-examination of Maxim Panel:
In response to a BCOAPA question, Maxim
agreed that its power would be BC
Clean.
BC Hydro cross-examination of
Maxim Panel:
BC Hydro queried the gas price risk in the Maxim proposal. Maxim
agreed that
the CFT is an opportunity for it and that it expected to be
bidding into the
CFT process. Maxim agreed however, that most of its
opportunities are on the
lower mainland and that there is very little
co-generation on Vancouver
Island. BC Hydro asked a series of questions
regarding the analysis of
greenhouse co-generation operations that Maxim had
filed as part of its
evidence. Maxim agreed that its co-generation studies
would be available to
BC Hydro to review.
Commission Counsel
cross-examination of Maxim Panel:
Commission counsel queried the
co-generation facility in France that Maxim
has been involved with and also
had some questions regarding the
co-generation analysis that had been
previously provided.
Green Island Energy ("GIE") Panel:
GIE is an IPP
that is proposing to take over existing facilities at the
closed down pulp
mill in Gold River and use biomass in the existing boilers
to generate
electricity for sale to the market. In an opening statement, GIE
stated that
it supports the provincial energy policy and believes that its
project is 20
per cent cheaper than VIGP. Phase 1 and 2 of its project is
fully funded and
the facilities needed, including transmission lines, are
already in place and
the plant is connected to the grid. In addition, the
fuel supply for phases 1
and 2 is secured. GIE anticipates that it will bid
into the CFT process and
that it believes an independent overseer should be
involved, i.e. the BCUC or
some third party with no perceived conflict of
interest.
GSXCCC
cross-examination of GIE panel:
GSXCCC began with questions concerning the
size and capacity of the GIE
facility. The maximum generating capacity would
be 105 MW in two phases. GIE
also stated that the fuel supply is biomass from
a catchment area that
covers the west coast of North America, no natural gas
would be used in the
plant, although there would be some Bunker C oil used as
backup. GIE also
expects that it will receive GHG offsets for its project.
BCOAPA cross-examination of GIE panel:
The BCOAPA questioned whether the
Gold River project was BC Clean and GIE
answered in the affirmative. GIE also
stated that it would expect to retain
the GHG credits.
BC Hydro
cross-examination of GIE panel:
BC Hydro's questions were designed to elicit
further information about the
Gold River facility. GIE stated that is could
have both phases in place and
operating by 2004 and that GIE is in a position
to respond to the CFT
immediately. The plants hog fuel requirements are in
the MOU phase and that
20 year agreements would be possible to match the EPA
that BC Hydro would
sign with an IPP. The plant would use only 1% of the
available biomass in
the west coast biomass market. Most of the biomass would
be forestry
industry residue, urban wood and log sorting waste. Most of its
permits are
in place and they are based on wood fuel. The first phase does
not require
an EAO approval as it is only 45 MW. In phase 2, GIE may apply
for an
exemption from the EAO process. In addition, a preliminary
interconnect
study with BC Hydro has been completed. GIE confirmed that there
are no
First Nations issues with its facility and that there are no
electrical
constraints between Gold River and BC Hydro's substation in
Campbell River.
Commission Counsel cross-examination of GIE
Panel:
Commission counsel only had a couple of questions for the panel.
First, GIE
was asked if it would proceed with its Phase 1 even if BC Hydro
did not sign
an EPA with it. GIE stated that it would and expects that it
would sell its
energy into the wholesale market. It would also proceed with
Phase 2 on the
same basis.
The Commission Chair had no questions and the
GIE panel was excused. The
Chair announced that all undertakings and further
letters of comment were
due to be filed no later than Thursday, July 10,
2003.
Thus, the evidentiary phase of the VIGP hearing concluded after 13
days of
public hearings, ten of those in Nanaimo, including two night
sittings and
the balance in Vancouver.